The Last mile connectivity project aims to increasing electricity access to Kenyans and is implemented by the Kenya Power and REREC.
Under this Project, KPLC will maximize the utilization of the 40,000 existing distribution transformers spread across the country, while Rural Electrification and Renewable Energy Corporation will focus on expansion of MV and LV lines to improve reticulation in rural areas.
This project has contributed to an increase in number of connections. Since its inception, 1,039,143 customers had been to the grid as of 31st October 2022.
The street lighting project is intended to provide adequate public lighting to industrial/residential areas, commercial centers, roads, railway and public transport facilities and also to create a conducive environment for a 24-hour economy envisaged under Vision 2030. As of 31st October 2022, 183,283 lanterns had been installed.
The study began in September 2022 with Economic Consulting Associates LTD as the consultant. This study is being undertaken with the aim of assisting in addressing the following in the grid:
As of 31st December 2022 the consultant had provided the inception report, Legal and Regulation Review, and Utility-Scale Storage Review reports.
This study is being implemented by the state department for Energy through the Feedback Infra Private LTD consultants. The contract was signed on 26th January, 2022 and the consultant is expected to finish the study by 30th June 2023 as per latest contract extension.
The objective of the consultancy is to develop comprehensive and updated technical standards and specifications for design and construction of the distribution system. As at 31st December 2022 the consultant had provided the inception and interim reports. Currently the consultant is undertaking the final report draft preparation and capacity building.
The current LCPDP as at June 2022 breakdowns the power plan and projections from 2022 to 2041. The primary objective of LCPDP is to develop a capacity expansion plan to meet the projected demand at minimal cost.
The LCPDP also apprises stakeholders and investors of the Government’s intents for the power sector over the planning period, guided by the prevailing policy framework and supporting legislation.
The plan contains four main outputs from the studies carried out: the electricity demand forecast, the recommended generation expansion plan, a tariff evolution trend for the medium term period of the plan and the recommended transmission expansion plan. National Energy planning is anchored in the Energy Act No 1 of 2019 with the mandate given to the Cabinet Secretary in charge of Energy. Section 4-8 of the Act provides for development and updating of the National Energy Policy every five years and regular development and review of the Integrated National Energy Plan (INEP) consisting of coal, renewable energy and electricity, in addition to County Energy Plans. The LCPDP has the following critical plans:
i. Generation expansion plan:
Under the plan, the effective interconnected capacity is projected to rise from 2,919 MW in 2021 to 8,870 MW in 2041
ii. Transmission Plan:
In the medium term, the plan projects the network to expand by 6,218km in circuit length and 12,089MVA in substation capacity. Long term projections indicate an increase of 12,672kms in circuit length of transmission lines and 18,497MVA substation capacity.
iii. The Impact of the Expansion Plan on Climate Change
The plan shows very limited utilization of fossil fuels in the medium term and long-term. Greenhouse gas (GHG) emissions are forecasted at below 10 MtCO2e from 2022 due to the planned phasing out of medium speed diesel plants and promotion of renewable energy. Increased integration of renewable energy sources such as hydropower, wind, solar PV, and geothermal contributes to the global goal of “towards net zero emissions”. This also aligns to the national target, to abate GHG emissions by 32% by 2030 relative to the Business
As Usual (BAU) scenario of 143 MtCO2e as contained in the updated Nationally Determined Contribution (NDC). The recommended plan offers a good opportunity for climate change mitigation with emissions of 0.03MtCO2e (Reference demand scenario) compared to 41MtCO2e projected by 2030 from electricity generation under the National Climate Change Action Plan (NCCAP).
iv. Projected Electricity Tariffs
The plan projects the power generation cost per kWh and retail tariff.
v. Kenya National Electrification Strategy (KNES)
The Kenya National Electrification Strategy (KNES) developed in 2018 is the roadmap to achieving universal access to electricity as a key plank of powering the Country’s development agenda.
KNES is anchored on six (6) themes that taken together will define the means and process by which electrification expansion can be better organized and implemented during the period of rapid investment and accelerated implementation. The themes are:
This report provides the respective Long Term Plan (LTP) for the period 2015 (base year) to 2035. This LTP is the identification and analysis of suitable expansion paths of the Kenyan power system for that period, complying with the defined planning criteria and framework. This encompasses: